Sludge Dewatering Machine Troubleshooting Solutions
Here are the reasons:
- Flocculation problem. Before the sewage is treated by the sludge dewatering equipment system, preliminary chemical treatment is necessary. After the sewage is flocculated and precipitated, it is pumped into the equipment for dehydration. The compatibility of the agent and sewage, the proportion of agent addition, the solubility of the agent, etc. will affect the size of flocs in the sewage. If the flocs are too small to meet the feed requirements, the mud will not be pressed dry.If the flocs are too large, they will bind more water and reduce the stickiness of the mud biscuits.
- The equipment is not debugged properly.First, we need to debug the flocculation effect of sewage.The second is to adjust the spindle speed and frequency. The third is to adjust the gap size of the back pressure plate and the flow rate of sewage into the mud outlet. The flow rate and the gap size of the back pressure plate need to be adjusted according to the actual conditions such as the characteristics of the sewage and the size of the flocs.
The solution is as follows:
- Pharmacy debugging is very important. First of all, we need to match the appropriate reagents according to the characteristics of our sewage treatment. Then adjust the proportion of the reagent added according to the speed and size of the flocculation alum flocs. This allows the sewage to reach a good flocculation state after entering the reaction tank.
- In addition to the adjustment of the reagent, the adjustment of the back pressure plate is also very important for the sludge dewatering machine. Therefore, after purchasing the sludge dewatering machine, it is best to find a professional technician to adjust it. In order to achieve better processing effect.
Here are the reasons:
- Equipment quality issues. Especially the flatness of the spiral shaft, movable ring and fixed ring. The spiral shaft and the ring piece are the dewatering body of the dewatering screw press. If the manufacturer cuts corners and removes the leveling process on the shaft and ring surfaces. Therefore, mud blockage is prone to occur during the use of the equipment.
- Sludge properties: Sludge is divided into organic sludge and inorganic sludge. The characteristics of organic sludge are high organic matter content, easy to decompose and stink, fine particles, low specific gravity, high water content and difficult to dehydrate, a hydrophilic substance with a colloidal structure, and easy to transport through pipes. The characteristics of inorganic sludge are just the opposite.
Dewatering screw press is used to treat sludge with too high inorganic content, or because the sludge has coarse particles, high specific gravity, and fast mud-water separation speed. However, the dewatering screw press has a low screw speed, which results in the sludge having a very low moisture content before it is discharged from the screw shaft filter chamber. Therefore, the mud cake is extremely lacking in fluidity and thus becomes clogged in the dewatering section. - Causes of improper operation.Different types of dewatering screw press correspond to different processing capacities. If the amount of sludge entering the dewatering screw press is much greater than its processing capacity, the dewatering screw press is overloaded.
The dewatering screw press was not cleaned and drained before and after use. If the residual sludge adheres between the spiral blades, it will cause the equipment to be blocked.
The solution is as follows:
- First, before use, let it idle for about 10 minutes, supplemented by a spray device.
After using the equipment, turn off the feed and let it idle for about 30 minutes. Allow the remaining sludge inside to be completely drained and clean the spiral blades with clean water. - If it is a minor blockage. You can try to reverse the dewatering screw press (the “frequency reverse” button on the PLC), or turn on the spray flushing to solve the problem.
- If it is a serious blockage, the operation should be stopped immediately, the equipment should be repaired and flushed with plenty of clean water. If necessary, remove the spiral shaft and clean the sludge attached to it.
- During the operation of the dewatering screw press, slight shaft blocking problems are inevitable. What is more important is to follow the operating requirements of the equipment during normal operation. Only by mastering the correct operating method can the problem of shaft blocking be avoided.
Here are the reasons:
- Equipment quality issues. The flatness between the fixed ring and the static ring of the sludge dewatering screw press is not enough or the ring thickness is not enough. During the use of the sludge dewatering screw press, the inner ring may be severely worn. This will cause the mud to leak and the ring will be squeezed and deformed after long-term use.
- The feed flow rate is too large. Different types of sludge dewatering screw press correspond to different processing capacities. The feed flow rate should be adjusted according to the actual processing conditions of the sludge dewatering screw press, reagent debugging, etc. If the feed flow is too large, it exceeds the range that the sludge dewatering screw press body can withstand. If the ring is overloaded, deformation may also occur.
- It depends on the nature of the sludge. The sludge contains a large amount of sand, oil, glue, solid garbage, etc. It will also cause an imbalance in the internal pressure, resulting in wear and deformation of the sludge dewatering screw press.
The solution is as follows:
- Before purchasing equipment, don’t just care about the price of the equipment, but also learn more about the quality of the product and after-sales service. Ensure that there is no problem with the quality of the equipment itself.
- Regarding the feed flow rate, it can be adjusted according to the valve. During installation, it is best to install an overflow pipe.
When the flocculation tank of the sludge dewatering screw press is overfilled, it will flow back through the overflow pipe. This can reduce the operating load on the sludge dewatering screw press ring. - Ensure the concentration of the feed to the sludge dewatering screw press (related to the adjustment of the reagent). If there are large slag blocks, metal impurities, etc. in the material, a filtering device must be added at the water inlet end.