Installation and Commissioning of Apoaqua Screw Press
Sludge Dewatering Machine Installation and Commissioning
Sludge Dewatering Screw Press Installation and Commissioning
Dewatering Screw Press Installation and Commissioning

Preparation before installation

  • Handling equipment: According to the weight and volume of the sludge dewatering machine. Determine the number of people to be moved and the tools to be used to move the equipment to ensure safe movement of the equipment.
  • Installation location: Select a flat and stable site to ensure the safety and normal operation of the equipment.
  • Equipment connection: Prepare the pipeline and power connections, and determine the connection method according to the installation location of the equipment.

Sludge Dewatering Machine Installation

  • Anchor bolt fixing: Place the equipment at the selected location and fix it with bolts.
  • Level adjustment: After the anchor bolts are fixed, use a level to adjust the level of the equipment.
  • Cable connection: Connect the power cable to the device and confirm that it is connected correctly.
  • Pipe connection: Connect the inlet and outlet water pipes of specified diameter to the equipment and confirm whether the connection is correct.

Sludge Dewatering Machine Debugging

  • Device startup: Press the device startup button to confirm whether the device starts normally. And observe the operation of the equipment.
  • Operation parameter setting: Set relevant operation parameters according to actual conditions, such as equipment rotation speed, online concentration monitoring, etc.
  • Equipment operation monitoring: After the sludge dewatering machine is started, the equipment operation monitoring is carried out. Including liquid level, pressure and temperature, etc.

Precautions

  • The installation location should be ventilated, dry and have sufficient water accumulation (not lower than the inlet of the sludge dewatering machine).
  • During installation, pay attention to the center of gravity of the equipment and ensure that the counterweight is firmly fixed to ensure stable operation of the equipment.
  • During installation, correct and appropriate accessories should be selected according to actual conditions to avoid component damage and unstable operation.
  • After installation, debug the equipment and adjust the operating parameters of the equipment to ensure normal operation of the equipment.

Solution

  • The sludge dewatering machine does not work properly after starting: First check whether the power is on, the cables are connected correctly, and the device is rotating in the correct direction. If all the above are normal, you need to check whether the engine motor, controller and other parts are faulty.
  • Equipment downtime during operation: Check whether the seawater pipeline is blocked. Check whether the water pump starts normally and whether there are any broken pipes or leakages.
  • The sludge dewatering machine encounters a power outage or a fuse blows during operation: Check whether the main electrical control board has poor heat dissipation. Are the switch and fuse too large or too small? Is there a problem with the network?